Certificate of Occupancy
Requirements for Obtaining Residential Certificate of Occupancy
Your request will be denied if the following are not completed:
- The Insulation Certificate uploaded to the permit. Click here for instructions on how to upload to the permit.
- All related permits, including temporary power, driveway access, and septic installation have approved final inspections or Certificate of Satisfactory Completion (if applicable).
- All Final Inspections Approved which includes Building, Plumbing, Electrical and Mechanical Final Inspections.
- System Development Charge (SDC Fees) must be paid in full.
- Visit the pay fees webpage to see if any fees are outstanding: Pay Fees
- SDC fees are due for replacement dwellings if the original dwelling was removed more than 2 years prior to final inspection on replacement dwelling.
- Final Planning and Infrastructure approval from City of La Pine or City of Sisters if New Dwelling is constructed in their jurisdictions
Requirements for Commercial Certificate of Occupancy
- All Conditions of Approval for Building and Planning must be met. You can find Structural Permit conditions in the documents section of the Commercial Structural Permit.
- Third Party Inspection reports must be uploaded to the permit when applicable. Please refer to Special Inspection Agreement for third party inspection requirements.
- Related Supplemental Mechanical, Electrical and Plumbing permits must have approved final inspections.
- Final Building inspection must be approved
- System Development Charge (SDC Fees) must be paid in full.